Project Management
Project management is the discipline of initiating, planning, executing, controlling, and closing the work of a team to achieve specific goals and meet specific success criteria. A project is a temporary endeavor designed to produce a unique product, service or result with a defined beginning and end (usually time-constrained, and often constrained by funding or deliverables) undertaken to meet unique goals and objectives, typically to bring about beneficial change or added value.[1][2]Business administration |
---|
![]() |
The temporary nature of projects stands in contrast with business as usual (or operations),[3] which are repetitive, permanent, or semi-permanent functional activities to produce products or services. In practice, the management of these two systems is often quite different, and as such requires the development of distinct technical skills and management strategies.[4]
The primary challenge of project management is to achieve all of the project goals and constraints.[5] This information is usually described in a user or project manual, which is created at the beginning of the development. The primary constraints are scope, time, quality and budget.[6] The secondary — and more ambitious — challenge is to optimize the allocation of necessary inputs and integrate them to meet pre-defined objectives.
History
Roman soldiers building a fortress, Trajan's Column 113 AD

Henry Gantt (1861–1919), the father of planning and control techniques
The 1950s marked the beginning of the modern project management era where core engineering fields come together to work as one. Project management became recognized as a distinct discipline arising from the management discipline with engineering model.[13] In the United States, prior to the 1950s, projects were managed on an ad-hoc basis, using mostly Gantt charts and informal techniques and tools. At that time, two mathematical project-scheduling models were developed. The "Critical Path Method" (CPM) was developed as a joint venture between DuPont Corporation and Remington Rand Corporation for managing plant maintenance projects. And the "Program Evaluation and Review Technique" or PERT, was developed by the United States Navy in conjunction with the Lockheed Corporation and Booz Allen Hamilton as part of the Polaris missile submarine program.[14]
PERT and CPM are very similar in their approach but still present some differences. CPM is used for projects that assume deterministic activity times; the times at which each activity will be carried out are known. PERT, on the other hand, allows for stochastic activity times; the times at which each activity will be carried out are uncertain or varied. Because of this core difference, CPM and PERT are used in different contexts. These mathematical techniques quickly spread into many private enterprises.
PERT network chart for a seven-month project with five milestones

The International Project Management Association (IPMA) was founded in Europe in 1967,[15] as a federation of several national project management associations. IPMA maintains its federal structure today and now includes member associations on every continent except Antarctica. IPMA offers a Four Level Certification program based on the IPMA Competence Baseline (ICB).[16] The ICB covers technical, contextual, and behavioral competencies.
In 1969, the Project Management Institute (PMI) was formed in the USA.[17] PMI publishes A Guide to the Project Management Body of Knowledge (PMBOK Guide), which describes project management practices that are common to "most projects, most of the time." PMI also offers multiple certifications.
Approaches
There are a number of approaches for managing project activities including lean, iterative, incremental, and phased approaches.Regardless of the methodology employed, careful consideration must be given to the overall project objectives, timeline, and cost, as well as the roles and responsibilities of all participants and stakeholders.
The traditional approach
A traditional phased approach identifies a sequence of steps to be completed. In the "traditional approach",[18] five developmental components of a project can be distinguished (four stages plus control):
Typical development phases of an engineering project
- initiation
- planning and design
- execution and construction
- monitoring and controlling systems
- completion and finish point
PRINCE2
Main article: PRINCE2
The PRINCE2 process model
PRINCE2 focuses on the definition and delivery of products, in particular their quality requirements. As such, it defines a successful project as being output-oriented (not activity- or task-oriented) through creating an agreed set of products[22] that define the scope of the project and provides the basis for planning and control, that is, how then to coordinate people and activities, how to design and supervise product delivery, and what to do if products and therefore the scope of the project has to be adjusted if it does not develop as planned.
In the method, each process is specified with its key inputs and outputs and with specific goals and activities to be carried out to deliver a project's outcomes as defined by its Business Case. This allows for continuous assessment and adjustment when deviation from the Business Case is required.
PRINCE2 provides a common language for all participants in the project. The governance framework of PRINCE2 – its roles and responsibilities – are fully described and require tailoring to suit the complexity of the project and skills of the organisation.[22]
Critical chain project management
Main article: Critical chain project management
Critical chain project management (CCPM) is a method of planning and
managing project execution designed to deal with uncertainties inherent
in managing projects, while taking into consideration limited
availability of resources (physical, human skills, as well as management
& support capacity) needed to execute projects.CCPM is an application of the theory of constraints (TOC) to projects. The goal is to increase the flow of projects in an organization (throughput). Applying the first three of the five focusing steps of TOC, the system constraint for all projects is identified as are the resources. To exploit the constraint, tasks on the critical chain are given priority over all other activities. Finally, projects are planned and managed to ensure that the resources are ready when the critical chain tasks must start, subordinating all other resources to the critical chain.
The project plan should typically undergo resource leveling, and the longest sequence of resource-constrained tasks should be identified as the critical chain. In some cases, such as managing contracted sub-projects, it is advisable to use a simplified approach without resource leveling.
In multi-project environments, resource leveling should be performed across projects. However, it is often enough to identify (or simply select) a single "drum". The drum can be a resource that acts as a constraint across projects, which are staggered based on the availability of that single resource.
One can also use a "virtual drum" by selecting a task or group of tasks (typically integration points) and limiting the number of projects in execution at that stage.
Process-based management
Main article: Process-based management
The incorporation of process-based management has been driven by the use of Maturity models such as the OPM3 and the CMMI (capability maturity model integration; see this example of a predecessor) and ISO/IEC15504
(SPICE – software process improvement and capability estimation).
Unlike SEI's CMM, the OPM3 maturity model describes how to make project
management processes capable of performing successfully, consistently,
and predictably in order to enact the strategies of an organization .Agile project management
Main article: Agile Project Management
The iteration cycle in agile project management
Advocates of this technique claim that:
- It is the most consistent project management technique since it involves frequent testing of the project under development.
- It is the only technique in which the client will be actively involved in the project development.
- The only disadvantage with this technique is that it should be used only if the client has enough time to be actively involved in the project.
- Scrum - A holistic approach to development that focuses on iterative goals set by the Product Owner through a backlog, which is developed by the Delivery Team through the facilitation of the Scrum Master.
- Extreme Programming (XP) - A set of practices based on a set of principles and values, with a goal to develop that provides real value by implementing tight feedback loops at all levels of the development process and using them to steer development. XP popularized Test Driven Development (TDD) and Pair Programming.
- eXtreme Manufacturing (XM) - An agile methodology based on Scrum, Kanban and Kaizen that facilitates rapid engineering and prototyping.
- Crystal Clear - An agile or lightweight methodology that focuses on colocation and osmotic communication.
- Kanban (看板?) - A lean framework for process improvement that is frequently used to manage work in progress (WIP) within agile projects. Kanban has been specifically applied in software development.
- Scrum ban a mixed scrum and kanban approach to project management. It focuses on taking the flexibility of kanban and adding the structure of scrum to create a new way to manage projects.
Lean project management
Main article: Lean project management
Lean project management uses the principles from lean manufacturing to focus on delivering value with less waste and reduced time.Extreme project management
Main article: Extreme project management
Planning and feedback loops in Extreme programming (XP) with the time frames of the multiple loops.
Using complex models for "projects" (or rather "tasks") spanning a few weeks has been proven to cause unnecessary costs and low maneuverability in several cases.[citation needed] The generalization of Extreme Programming to other kinds of projects is extreme project management, which may be used in combination with the process modeling and management principles of human interaction management.
Benefits realization management
Main article: Benefits realisation management
Benefits realization management (BRM) enhances normal project
management techniques through a focus on outcomes (the benefits) of a
project rather than products or outputs, and then measuring the degree
to which that is happening to keep a project on track. This can help to
reduce the risk of a completed project being a failure by delivering
agreed upon requirements/outputs but failing to deliver the benefits of those requirements.In addition, BRM practices aim to ensure the alignment between project outcomes and business strategies. The effectiveness of these practices is supported by recent research evidencing BRM practices influencing project success from a strategic perspective across different countries and industries.[24]
An example of delivering a project to requirements might be agreeing to deliver a computer system that will process staff data and manage payroll, holiday and staff personnel records. Under BRM the agreement might be to achieve a specified reduction in staff hours required to process and maintain staff data.
Processes
The project development stages[25]
- Initiation
- Planning
- Production or execution
- Monitoring and controlling
- Closing
Initiating
Initiating process group processes[25]

The initiating stage should include a plan that encompasses the following areas:
- analyzing the business needs/requirements in measurable goals
- reviewing of the current operations
- financial analysis of the costs and benefits including a budget
- stakeholder analysis, including users, and support personnel for the project
- project charter including costs, tasks, deliverables, and schedules
Planning
After the initiation stage, the project is planned to an appropriate level of detail (see example of a flow-chart).[25] The main purpose is to plan time, cost and resources adequately to estimate the work needed and to effectively manage risk during project execution. As with the Initiation process group, a failure to adequately plan greatly reduces the project's chances of successfully accomplishing its goals.Project planning generally consists of[27]
- determining how to plan (e.g. by level of detail or Rolling Wave planning);
- developing the scope statement;
- selecting the planning team;
- identifying deliverables and creating the work breakdown structure;
- identifying the activities needed to complete those deliverables and networking the activities in their logical sequence;
- estimating the resource requirements for the activities;
- estimating time and cost for activities;
- developing the schedule;
- developing the budget;
- risk planning;
- gaining formal approval to begin work.
For new product development projects, conceptual design of the operation of the final product may be performed concurrent with the project planning activities, and may help to inform the planning team when identifying deliverables and planning activities.
Executing
Executing process group processes[25]
Monitoring and controlling
Monitoring and controlling process group processes[25]
Monitoring and controlling includes:[28]
- Measuring the ongoing project activities ('where we are');
- Monitoring the project variables (cost, effort, scope, etc.) against the project management plan and the project performance baseline (where we should be);
- Identify corrective actions to address issues and risks properly (How can we get on track again);
- Influencing the factors that could circumvent integrated change control so only approved changes are implemented.
Project maintenance is an ongoing process, and it includes:[6]
- Continuing support of end-users
- Correction of errors
- Updates to the product over time
Monitoring and controlling cycle
Over the course of any construction project, the work scope may change. Change is a normal and expected part of the construction process. Changes can be the result of necessary design modifications, differing site conditions, material availability, contractor-requested changes, value engineering and impacts from third parties, to name a few. Beyond executing the change in the field, the change normally needs to be documented to show what was actually constructed. This is referred to as change management. Hence, the owner usually requires a final record to show all changes or, more specifically, any change that modifies the tangible portions of the finished work. The record is made on the contract documents – usually, but not necessarily limited to, the design drawings. The end product of this effort is what the industry terms as-built drawings, or more simply, “as built.” The requirement for providing them is a norm in construction contracts. Construction document management is a highly important task undertaken with the aid an online or desktop software system, or maintained through physical documentation. The increasing legality pertaining to the construction industries maintenance of correct documentation has caused the increase in the need for document management systems.
When changes are introduced to the project, the viability of the project has to be re-assessed. It is important not to lose sight of the initial goals and targets of the projects. When the changes accumulate, the forecasted result may not justify the original proposed investment in the project. Successful project management identifies these components, and tracks and monitors progress so as to stay within time and budget frames already outlined at the commencement of the project.
Closing
Closing process group processes.[25]
This phase consists of:[6]
- Contract closure: Complete and settle each contract (including the resolution of any open items) and close each contract applicable to the project or project phase.
- Project close: Finalize all activities across all of the process groups to formally close the project or a project phase
Project controlling and project control systems
Project controlling should be established as an independent function in project management. It implements verification and controlling function during the processing of a project in order to reinforce the defined performance and formal goals.[29] The tasks of project controlling are also:- the creation of infrastructure for the supply of the right information and its update
- the establishment of a way to communicate disparities of project parameters
- the development of project information technology based on an intranet or the determination of a project key performance indicator system (KPI)
- divergence analyses and generation of proposals for potential project regulations[30]
- the establishment of methods to accomplish an appropriate project structure, project workflow organization, project control and governance
- creation of transparency among the project parameters[31]
- investment analysis
- cost–benefit analysis
- value benefit analysis
- expert surveys
- simulation calculations
- risk-profile analysis
- surcharge calculations
- milestone trend analysis
- cost trend analysis
- target/actual-comparison[32]
Control systems are needed for cost, risk, quality, communication, time, change, procurement, and human resources. In addition, auditors should consider how important the projects are to the financial statements, how reliant the stakeholders are on controls, and how many controls exist. Auditors should review the development process and procedures for how they are implemented. The process of development and the quality of the final product may also be assessed if needed or requested. A business may want the auditing firm to be involved throughout the process to catch problems earlier on so that they can be fixed more easily. An auditor can serve as a controls consultant as part of the development team or as an independent auditor as part of an audit.
Businesses sometimes use formal systems development processes. These help assure that systems are developed successfully. A formal process is more effective in creating strong controls, and auditors should review this process to confirm that it is well designed and is followed in practice. A good formal systems development plan outlines:
- A strategy to align development with the organization’s broader objectives
- Standards for new systems
- Project management policies for timing and budgeting
- Procedures describing the process
- Evaluation of quality of change
Topics
Project managers
A project manager is a professional in the field of project management. Project managers can have the responsibility of the planning, execution, and closing of any project, typically relating to construction industry, engineering, architecture, computing, and telecommunications. Many other fields in production engineering, design engineering, and heavy industrial have project managers.A project manager is the person accountable for accomplishing the stated project objectives. Key project management responsibilities include creating clear and attainable project objectives, building the project requirements, and managing the triple constraint for projects, which is cost, time, and scope.
A project manager is often a client representative and has to determine and implement the exact needs of the client, based on knowledge of the firm they are representing. The ability to adapt to the various internal procedures of the contracting party, and to form close links with the nominated representatives, is essential in ensuring that the key issues of cost, time, quality and above all, client satisfaction, can be realized.
Project management types
Project management can apply to any project, but it is often tailored to accommodate the specific needs of different and highly specialized industries. For example, the construction industry, which focuses on the delivery of things like buildings, roads, and bridges, has developed its own specialized form of project management that it refers to as Construction project management and for which project managers can become trained and certified in.[34] The Information technology industry has also evolved to develop its own form of Project management that is referred to as IT Project management and which specializes in the delivery of technical assets and services that are required to pass through various lifecycle phases such as planning, design, development, testing, and deployment. Biotechnology project management focuses on the intricacies of biotechnology research and development.[35]For each type of project management, project managers develop and utilize repeatable templates that are specific to the industry they're dealing with. This allows project plans to become very thorough and highly repeatable, with the specific intent to increase quality, lower delivery costs, and lower time to deliver project results.
Work breakdown structure
Main article: Work breakdown structure
The work breakdown structure (WBS) is a tree structure
that shows a subdivision of effort required to achieve an objective—for
example a program, project, and contract. The WBS may be hardware-,
product-, service-, or process-oriented (see an example in a NASA reporting structure (2001)).[36]A WBS can be developed by starting with the end objective and successively subdividing it into manageable components in terms of size, duration, and responsibility (e.g., systems, subsystems, components, tasks, sub-tasks, and work packages), which include all steps necessary to achieve the objective.[20]
The work breakdown structure provides a common framework for the natural development of the overall planning and control of a contract and is the basis for dividing work into definable increments from which the statement of work can be developed and technical, schedule, cost, and labor hour reporting can be established.[36] The work breakdown structure can be displayed in two forms one in form of a table with subdivision of tasks two in form of an organisational chart.
International standards
There have been several attempts to develop project management standards, such as:- ISO 21500: 2012 - Guidance on project management. This is the first project management ISO.
- ISO 31000: 2009 - Risk management. Risk management is 1 of the 10 knowledge areas of either ISO 21500 or PMBoK5 concept of project management.
- ISO/IEC/IEEE 16326-2009 - Systems and Software Engineering—Life Cycle Processes—Project Management [37]
- Capability Maturity Model from the Software Engineering Institute.
- GAPPS, Global Alliance for Project Performance Standards – an open source standard describing COMPETENCIES for project and program managers.
- A Guide to the Project Management Body of Knowledge from the Project Management Institute (PMI)
- HERMES method, Swiss general project management method, selected for use in Luxembourg and international organizations.
- The ISO standards ISO 9000, a family of standards for quality management systems, and the ISO 10006:2003, for Quality management systems and guidelines for quality management in projects.
- PRINCE2, Projects IN Controlled Environments.
- Association for Project Management Body of Knowledge[38]
- Team Software Process (TSP) from the Software Engineering Institute.
- Total Cost Management Framework, AACE International's Methodology for Integrated Portfolio, Program and Project Management.
- V-Model, an original systems development method.
- The Logical framework approach, which is popular in international development organizations.
- [Australian Institute of Project Management] AIPM has 4 levels of certification; CPPP, CPPM, CPPD & CPPE for Certified Practicing Project ... Partner, Manager, Director and Executive.
Project portfolio management
Main article: Project portfolio management
An increasing number of organizations are using, what is referred to as, project portfolio management (PPM) as a means of selecting the right projects and then using project management techniques[39] as the means for delivering the outcomes in the form of benefits to the performing private or not-for-profit organization.Project management software
Main articles: Project management software and Project management information system
Project management software
is software used to help plan, organize, and manage resource pools,
develop resource estimates and implement plans. Depending on the
sophistication of the software, functionality may include estimation and planning, scheduling, cost control and budget management, resource allocation, collaboration software, communication, decision-making, workflow, quality management, documentation and/or administration systems.[40][41]Virtual project management
Main article: Virtual team
Virtual program management (VPM) is management of a project done by a virtual team, though it rarely may refer to a project implementing a virtual environment[42] It is noted that managing a virtual project is fundamentally different from managing traditional projects,[43] combining concerns of telecommuting and global collaboration (culture, timezones, language).[44]